X’inhu Chart ta’ Gantt?

Chart ta’ Gantt ipoġġi l-kompiti fuq kalendarju b’tul ta’ żmien, dipendenzi u milestones. Huwa l-istandard tal-immaniġġjar tal-proġetti biex juri min jagħmel xiex, meta, u xiex jiddependi fuq xiex.

Eżempju live

Kodiċi Mermaid
gantt
    title Product Launch
    dateFormat YYYY-MM-DD
    section Design
      Wireframes       :a1, 2026-01-05, 10d
      UI design        :a2, after a1, 14d
    section Build
      Backend API      :b1, 2026-01-12, 21d
      Frontend         :b2, after a2, 18d
    section Launch
      Beta testing     :c1, after b2, 10d
      Go live          :milestone, after c1, 0d
Eżempju live
2026-01-112026-01-182026-01-252026-02-012026-02-082026-02-152026-02-22Wireframes Backend API UI design Frontend Beta testing Go live DesignBuildLaunchProduct Launch

Meta tużah

Ippjana tnedijiet ta’ prodotti u skedi ta’ rilaxx
Ikkomunika roadmaps lill-partijiet interessati
Segwi fażijiet ta’ sprint jew migrazzjoni bid-dipendenzi

Sintassi bażika

.mmd
gantt
    dateFormat YYYY-MM-DD
    section Phase 1
      Task A :a1, 2026-01-01, 7d
      Task B :after a1, 5d

Mistoqsijiet dwar din id-dijagramma

Il-kompiti jistgħu jiddependu fuq xulxin?

Iva — uża “after taskId” biex torbot il-kompiti f’katina, u milestones biex timmarka dati ewlenin. Is-sezzjonijiet jiġbru l-kompiti skont il-linja tax-xogħol jew it-tim.

Gantt ibbażat fuq test huwa aħjar minn għodda tal-proġetti?

Għall-komunikazzjoni, iva: jgħix fid-docs tiegħek, jiġi verżjonat ma’ git, u jiġi aġġornat f’sekondi. Għall-immaniġġjar tar-riżorsi, użah flimkien mal-għodda PM tiegħek.

Oħloq il-Chart ta’ Gantt tiegħek issa

Iddeskrivih b’lingwa naturali — l-AI tikteb il-kodiċi Mermaid għalik.